For more information and Full Evaluation Report, Click here
                  
During
                    schematic design, the study team will continue to develop
                    these alternatives to a higher level of detail and incorporate,
                    as appropriate, comments and concerns from the project's public
                    and study work groups. The following are key concerns raised
                    during the Phase 2 alternative refinement and which the designers
                    will remain aware of during schematic design: 
                  
                    - 
                      Include opportunities for urban design
 
                    - Minimize
                      business and right-of-way impacts
 
                    - Maximize/lengthen
                      weaving areas between ramps
 
                    - Allow
                      for improved access/circulation 
 
                  
                  
                  During
                    the Phase 2 refinement of the alternatives, the study team
                    continued to develop the alternatives from Phase 1 to a higher
                    level of detail and incorporate, as appropriate, comments
                    and concerns from the public and study work groups. The following
                    are concerns raised during the first phase of alternative
                    development: 
                  
                    - Include
                      opportunities for urban design 
 
                    - Include
                      access from Woodall Rodgers to DNT 
 
                    - Freeway
                      to freeway access is improved but local access is more limited
                      
 
                    - Provide
                      more direct access to/from the Industrial Boulevard area,
                      Colorado Boulevard, and Beckley Avenue - Cadiz should not
                      be made one-way
 
                    - Minimize
                      impacts to businesses and right-of-way impacts, especially
                      in the Mixmaster area - Utilize the recently completed northbound
                      IH 35E/HOV bridge 
 
                    - Check
                      for planned development districts along the corridor which
                      could escalate right-of-way costs 
 
                    - Maximize/lengthen
                      weaving areas between ramps 
 
                    - Include
                      more quantitative information 
 
                  
                  The
                    study team refined the remaining alternatives between August
                    and December 2002. During this time, meetings continued with
                    the Project Coordination and Community work groups. Public
                    Meetings were held in January 2003 to gain additional public
                    input. After the Public Meetings, the preferred alternative
                    was selected for final revisions per agency/public input.
                    This preferred alternative will be further refined during
                    Phase 3 - Schematic Design. 
                  During
                    Phase 2, the study team developed the conceptual designs from
                    Phase 1 that were selected for further evaluation. To allow
                    for public review and comment, the alternatives have been
                    placed on this website for information purposes only. PLEASE
                    NOTE, THESE PRELIMINARY PROJECT LAYOUTS ARE NOT INTENDED FOR
                    CONSTRUCTION, BIDDING OR PERMIT PURPOSES AND ARE SUBJECT TO
                    CHANGE WITHOUT NOTICE. Larger drawings were displayed at Public
                    Meetings held in January 2003. The following maps are in pdf
                    format: 
                  
                    
                      | The
                        PDF items are in Adobe Acrobat® Portable Document Format
                        (PDF). Notice: The mentioning of brand names is
                        strictly for informational purposes and does not imply
                        endorsement or advertisement of a particular product by
                        the Texas Department of Transportation. Acrobat is a registered
                        trademark of Adobe System, Incorporated. The reader may
                        be downloaded from Adobe at: http://www.adobe.com/prodindex/acrobat/readstep.html
                          | 
                    
                  
                  
                    Phase 2: IH 30 Canyon from
                    IH 35E to IH 45 (as of November 2002) 
                  Phase
                    2: IH 30/IH 35E Mixmaster Interchange 
                  
                  Phase
                    2: IH 35E Stemmons from Commerce to the Oak Lawn (as of November
                    2002)
                    Phase 2: IH 35E Stemmons
                    from Oak Lawn to Motor Street (as of February 2003) 
                    Phase 2: IH 35E Stemmons
                    from Motor Street to Empire Central (as of February 2003)
                    
                  
                  The
                    Phase 1 Conceptual Alternative Development developed numerous
                    alternatives and then evaluated them to determine how well
                    the alternatives addressed the identified objectives of the
                    Project Pegasus. Alternatives were compared to each other
                    and the No-Build Alternative using an established set of evaluation
                    criteria for traffic conditions in the design year of 2026.
                    The application of criteria and measures was intended to pinpoint
                    the major differences between alternatives, help facilitate
                    the decision of which alternative(s) should be developed further
                    in Phase 2, and balance design standards, safety, transportation
                    needs, costs, and social, economic, and environmental concerns.
                    
                  Based
                    on the evaluation measures and criteria established, the following
                    alternatives have been recommended for further development
                    and evaluation: 
                  
                    - No-Build
                      Alternative 
 
                    - IH
                      30 Canyon 
                      
                    
 
                    - IH
                      30/IH 35E Mixmaster 
                      
                        - Alternative
                          M-1 
 
                        - Alternative
                          M-2 
 
                      
                     
                    - IH
                      35E Lower Stemmons
                      
                        - Alternative
                          S-1 between Commerce and Oak Lawn
 
                        - Alternative
                          S-2C between Oak Lawn and Empire Central
 
                      
                     
                  
                  For
                    more information and the full evaluation report, click
                    here. 
                  PLEASE NOTE,
                    THESE PRELIMINARY PROJECT LAYOUTS ARE NOT INTENDED FOR CONSTRUCTION,
                    BIDDING OR PERMIT PURPOSES AND ARE SUBJECT TO CHANGE WITHOUT
                    NOTICE. 
                  During
                    Phase 1, the study team has developed numerous conceptual
                    alternatives. To allow for public review and comment, the
                    alternatives have been placed on this website for information
                    purposes only. Larger drawings were displayed at the May 2002
                    Public Meetings (see Events Calendar for meeting summaries).
                    The following maps are in pdf format: 
                  Phase
                  1 : IH 30 Canyon Section: from
                  IH 35E to IH 45 
                  
                  
                  Phase
                    1 : Mixmaster: IH 35E/IH 30 Interchange 
                  
                    - Alternative
                      M-1 (2.6mb) Updated May 28, 2002
 
                    - Alternative
                      M-2 (2.6mb) Updated May 28, 2002
 
                    - Alternative
                      M-3 - Note: This drawing has not been developed
                      to the same level as M-1 or M-2 because realigning IH 35E
                      east of the TXU substation would introduce a more severe
                      geometric design than the existing alignment. 
 
                    - Alternative
                      M-4 - Note: This drawing has not been developed to the
                      same level as M-1 or M-2 because of potential environmental
                      issues regarding elevating IH 35E over the Houston Street
                      Viaduct near downtown. If these issues can be resolved,
                      the design of the frontage and collector-distributor roads
                      will be included and would be similar to those shown in
                      M-2. 
 
                  
                  Phase
                    1 : IH35E Lower Stemmons: IH 30 to Dallas North Tollway 
                  Phase
                    1 : IH 35E from Oak Lawn to Wycliff (4.6mb)
                  Phase
                    1 : IH 35E from Wycliff to North of Dolton (4.5mb)
                  Phase
                    1 : IH 35E from North of Dolton to South of Commonwealth
                    (4.6mb)
                  Phase
                    1 : IH 35E/SH 183 Interchange (5.0mb) Updated
                    May 28, 2002
                  
                  Preliminary
                    recommended improvements from the Trinity Parkway Corridor
                    MTIS for IH 30, IH 35E, and the Mixmaster interchange include
                    the following major elements: 
                  
                    - Building
                      additional main lanes along the south side of the IH 30
                      Canyon to carry eastbound traffic, allowing the existing
                      eastbound IH 30 main lanes to be reconfigured for two-way
                      High Occupancy Vehicle(HOV) use through the area. 
 
                    - Adding
                      collector-distributor roads along both sides of the IH 30
                      Canyon, beginning in the area of IH 45, and terminating
                      into Griffin Street East and West in the area of Ervay Street.
                      These particular frontage roads would be controlled-access
                      and specifically necessary for traffic management and capacity
                      purposes.
 
                    - Reconfiguring
                      the IH 30/IH 35E Mixmaster to allow through traffic on IH
                      30 and IH 35E to stay in the same lanes through the interchange,
                      rather than being forced to change lanes as in the current
                      configuration. Adding north-south lanes through the Mixmaster,
                      so that IH 35E traffic flows on a total of three (3) dedicated
                      main lanes in each direction. 
 
                    - Adding
                      direct-connect ramps in the Mixmaster connecting IH 35E
                      (South R.L. Thornton Freeway) to the IH 30 (Tom Landry Highway)
                      for the northbound to westbound and eastbound to southbound
                      traffic movements. 
 
                    - Constructing
                      collector-distributor roads on both sides of IH 35E (Lower
                      Stemmons) from the Reunion Arena area northward to Oak Lawn
                      Avenue. These particular frontage roads would be controlled-access
                      and specifically necessary for traffic management and capacity
                      purposes.
 
                    - Constructing
                      continuous collector-distributor roads alongside IH 35E
                      in the segment from Spur 366(Woodall Rodgers Freeway) to
                      the connection with the Dallas North Tollway, with allowance
                      for separating traffic streams to and from Spur 366 (the
                      Woodall Rodgers Freeway) and the Dallas North Tollway. 
 
                    - Construction
                      of collector-distributor roads over the Trinity River along
                      both IH 30 and IH 35E. 
 
                    - Constructing
                      an HOV system serving the major radial highways feeding
                      into the Dallas Central Business District (CBD). 
 
                  
                  
                  Based
                    on the results of the Trinity Parkway Corridor MTIS, TxDOT
                    is beginning the second phase of project development for the
                    proposed reconstruction and widening of IH 30 and IH 35E in
                    Dallas County. This phase involves developing the Preliminary
                    Engineering (PE) and Environmental Assessment (EA) in accordance
                    with state and federal guidelines. Alternative development
                    and evaluation, public and agency involvement, schematic design,
                    urban design, and right-of-way and utility mapping are included.
                    The environmental documentation will be in the form of an
                    EA. The schedule for this effort is 36-months. This combined
                    planning effort will conclude with:
                  
                    - 
                      Identification of a Locally Preferred Alternative (LPA),
                      
 
                    - Typical
                      cross-sections, 
 
                    - Design
                      schematic, 
 
                    - Interstate
                      access justification, and 
 
                    - Final
                      environmental clearance through a Finding of No Significant
                      Impact (FONSI). 
 
                  
                  Planning
                    Schedule 
                  
                  
The
                    general process for building large transportation projects
                    involves many steps and can take 10 to 15 years before roadway
                    improvements are open to traffic. The flowchart on the left
                    shows the major steps. 
                  Regional
                    transportation needs are identified through a long-range planning
                    process involving local, regional, state and federal transportation
                    officials (Step 1). 
                  The
                    process is based on current needs, future growth and available
                    transportation funding and the Metropolitan Transportation
                    Plan (MTP) for the next 20 years (Step 2). If warranted, Major
                    Investment studies are conducted during this process. 
                  After
                    a project is included in the MTP, corridor-level planning
                    studies can begin. This step includes the development and
                    evaluation of alternatives, public and agency involvement,
                    environmental studies, preliminary design, and cost estimates
                    (Step 3). These more detailed planning studies will both determine
                    if a transportation project is feasible and will identify
                    potential effects on the community and environment. 
                  Once
                    these studies are completed and approved by the Federal Highway
                    Administration (FHWA), more engineering is initiated to develop
                    detailed construction plans and right-of-way maps (Step 4).
                    
                  Based
                    on the construction plans, the necessary right-of-way for
                    the project is acquired and any utilities such as power lines
                    and water lines can be relocated such that they do not interfere
                    with construction (Step 5). 
                  When
                    the construction plans are completed, right-of-way acquired,
                    and funding secured - construction can begin (Step 6). As
                    with most large projects, it is anticipated the improvements
                    to IH 30 and IH 35E will be built in stages and could take
                    5 to 10 years to complete (Step 7). 
                  
                  Click
                    here to go to information about
                    Road Rage and how to avoid it.